Allen County lands $27.9 million to design and build a Scott Road railroad overpass
The Fort Wayne Today team
If you cross the tracks on Scott Road, a main north-south artery on the county's west side, this one's for you. Allen County received the full $27,878,116 it requested from the Federal Railroad Administration's Railroad Crossing Elimination grant program. County officials say separating the road and rail lines will improve safety, reduce traffic delays and help emergency responders.
$27,878,116federal grant for the Scott Road rail crossing project
It covers project development, final design and construction of the C.R.O.S.S. Scott Road Project.
Sources: WPTA 21Alive, WOWO
The money lets the team develop its concepts, acquire right-of-way and relocate utilities. Then comes the grade separation over the Norfolk Southern crossing.
“This is about making sure our transportation infrastructure keeps pace with the growth of our community.”
- Crossing: Norfolk Southern Railway at Scott Road
- Earlier grant: up to $400,000, used to evaluate alternatives
- By year's end: conceptual engineering and a preliminary environmental assessment
Design starts in 2027 and construction should wrap up in 2032
- Jan. 2025Earlier federal grant of up to $400,000 is given to study alternatives
- Dec. 2026Current planning stage is scheduled to be completed
- 2027Design work for the Scott Road grade separation should begin in late summer
- Fall 2032Construction of the grade separation should be completed